Supportive housing
Homekey Rohnert Park — Labath Landing
- Scale
- 60 rooms / 16 modules
- Location
- Rohnert Park, California
- Client
- City of Rohnert Park
- Project duration
- March 2022 – October 2022
- Production to ribbon
- 3.5 months
- Homekey round
- 2
Sixteen modules. Sixty private rooms. Three and a half months from production start to ribbon-cutting at 90% occupancy — the second Homekey Round 2 project to come online in all of California.
Timeline
- March 2022 — Contract signed, production begins on the assembly line
- Weekly — Client receives visual progress updates from the factory floor, tracking each module station by station
- October 23, 2022 — Ribbon cutting, 90% occupancy
What we delivered
Sixteen Connect Shelter modules configured as 60 private, dignified rooms. Each module completed every assembly-line station — framing, MEP rough, envelope, drywall, paint, interior finish, QC — before shipping to site 100% complete.
The client-update discipline
Every week of production, the Rohnert Park team received visual updates showing where each of their modules was on the assembly line. That visibility — impossible with conventional construction — is what makes a 3.5-month timeline trustworthy to a public client.