Supportive housing

Homekey Rohnert Park — Labath Landing

Scale
60 rooms / 16 modules
Location
Rohnert Park, California
Client
City of Rohnert Park
Project duration
March 2022 – October 2022
Production to ribbon
3.5 months
Homekey round
2

Sixteen modules. Sixty private rooms. Three and a half months from production start to ribbon-cutting at 90% occupancy — the second Homekey Round 2 project to come online in all of California.

Timeline

  • March 2022 — Contract signed, production begins on the assembly line
  • Weekly — Client receives visual progress updates from the factory floor, tracking each module station by station
  • October 23, 2022 — Ribbon cutting, 90% occupancy

What we delivered

Sixteen Connect Shelter modules configured as 60 private, dignified rooms. Each module completed every assembly-line station — framing, MEP rough, envelope, drywall, paint, interior finish, QC — before shipping to site 100% complete.

The client-update discipline

Every week of production, the Rohnert Park team received visual updates showing where each of their modules was on the assembly line. That visibility — impossible with conventional construction — is what makes a 3.5-month timeline trustworthy to a public client.

Gallery
Homekey Rohnert Park — Labath Landing — photo 1Homekey Rohnert Park — Labath Landing — photo 2
Related Shelters

Shelters used on this project

See all six Shelters

Rapid-deploy modular shelter. Built in a factory. Delivered in days.